Installation of the ninth support tower of the passenger cable car across the Oka under construction was a construction milestone in Nizhny Novgorod on November 17, 2026. On that day, JSC Urbantech Cable Cars completed the assembly of the shore tower on Pravdinskaya Street near the left bank of the river.[1]

Characteristics of the tower

The assembled structure is more than 70 meters tall — comparable to a 20-story building — and became the tallest of all the towers installed along the route as of the date of the event.[2] It is also the first of the three lattice towers provided for in the project: the previous eight towers, assembled on the section between the future "Zarechnaya" and "Tikhaya Gavan" stations, have a tubular construction.[3] The tower is assembled from ten sections and is equipped with four crossarms and 56 rollers to compensate for dynamic loads.[3]

Assembly had been under way since late October 2026, using special lifting equipment. The assembly was preceded by a preparatory stage: relocation of utility lines, construction of pile foundations, and large-block assembly of the metal structures; at every stage the work was accompanied by geodetic monitoring.[1]

Place in the project

The ninth tower is located on the left bank of the Oka. The design span between the shore towers in the Zarechye and Upper Town parts of the city will be 808 meters.[4] On the upper bank, near the Okeanis water park on Gagarin Avenue, the third station of the cable car will be located.[2] The "Zarechnaya" station is planned near the former Rossiya movie theater, and the "Tikhaya Gavan" station in the area of Bauman Street.[2]

The total length of the line will be 3,340 meters, with 60 cabins running along it. The trip between the Zarechye (Lower Town across the Oka) and Upper Town sections will take about 15 minutes, compared with 40 minutes by car across the Molitovsky Bridge. The design daily ridership is 10,000 people, and the maximum capacity is 30,500 passengers.[3] Construction is being carried out by Urbantech Cable Cars JSC under a concession agreement with the Nizhny Novgorod Region government; work began in August 2025, and the cable car is scheduled to launch in 2027.[1]

Sources

  1. NIA "Nizhny Novgorod" — A 70-meter cable car tower across the Oka has been installed in Nizhny Novgorod. Nizhny Novgorod News
  2. GIPERNN — Height of more than 70 meters: the ninth tower of the new cable car across the Oka has been installed
  3. Vremya N — Assembly of one of the tallest cable car towers across the Oka completed in Nizhny Novgorod
  4. Newsroom24 — A cable car tower for passengers across the Oka has been erected in Nizhny Novgorod — Transport
  5. Pro Gorod Nizhny Novgorod — A record-breaking 70-meter cable car tower across the Oka has been erected in Nizhny Novgorod