In November 2026, the reconstruction of the Triumphal Arch in Nizhny Novgorod ran into a delay: during construction work, it turned out that a significant number of utility lines run through the construction zone and must be relocated and rebuilt.[1][2]
Reasons for the delay
According to the Department of Construction and Capital Repairs, the utility lines discovered in the construction zone must be relocated and rebuilt.[2] This required additional approvals from the utility providers, as well as work to identify the owners of the discovered networks.[1][2] In addition, it was necessary to make adjustments to the design and cost estimate documentation.[1]