In November 2026, the Governor of Nizhny Novgorod Region Gleb Nikitin announced that the opening of two new metro stations — Sennaya and "Freedom Square" — is being postponed: commissioning tests on the section of the Avtozavodskaya Line now under construction are planned to begin no earlier than 2028.[1][2] The improvement of the surrounding areas is expected to be completed by the same year.[2]

History of the postponements

Preparation of the sites for the metro extension in the upper part of the city began in 2022, and construction work proper began in 2023. Both stations were originally scheduled for completion by the end of 2025, then the deadline was pushed back to 2026, and later to the end of summer 2027.[1] Over that time, the cost of construction has risen from approximately 35.5 billion rubles to almost 48 billion. The general contractor is Mosproekt-3.[1]

Causes of the delay and progress of the work

Governor Nikitin explained that a metro construction period of five to six years is standard practice for large cities. In the center of Nizhny Novgorod, the work is further complicated by the high concentration of cultural heritage sites, historic buildings, and underground utilities.[3][4] "Postponed deadlines affect virtually all major construction projects. In our country, you can't help but set ambitious deadlines," he said.[1]

By the time of the announcement, the tunnels between the Sennaya and Ploshchad Svobody stations had been fully bored in 2024–2025; preparations for laying the rails were under way. At the same time, Mosproekt-3 continued tunneling on the section from Gorkovskaya station to Freedom Square and was building the station complexes.[1][2]

Sormovskaya Station

The same contractor, Mosproekt-3, is building Sormovskaya station in the Sormovo district (the lower part of the city). According to Nikitin, preparation of the construction site is about 95% complete: properties slated for demolition had to be bought out, and some issues were resolved through the courts. Work on the design documentation is also being completed in parallel.[1][2] Sormovskaya was originally expected to open in 2026, but the deadline was later pushed back to 2029.[1] The Governor expressed the view that building it will be easier than building the stations of the Avtozavodskaya Line in the upper part of the city, since the Sormovo district does not have such dense historic buildings.[3]

Shortly before Nikitin's statement, he discussed the construction of the Nizhny Novgorod metro with Deputy Prime Minister of the Russian Federation Marat Khusnullin, who urged that the progress of the work be kept under strict control.[3]

Sources

  1. GIPERNN — Two new metro stations in Nizhny Novgorod will not open before 2028
  2. NIA "Nizhny Novgorod" — When the new metro stations in Nizhny Novgorod will open: Nikitin's answer. Nizhny Novgorod News
  3. Newsroom24 — Governor Nikitin named the timeline for commissioning tests of the metro in Nizhny Novgorod — Transport
  4. Zhivyom v Nizhnem — Gleb Nikitin explained the postponement of opening dates for Nizhny Novgorod metro stations — Zhivem v Nizhnem