On August 7, 2026, during the trial of the former general director of Teploenergo JSC Ilya Khalturin, his defense filed a motion to terminate the criminal prosecution on the grounds that no crime had been committed. The document ran to about 200 pages.[1]

The substance of the charges

Khalturin is charged with abuse of official powers on four counts. The first concerns a change of design organization during the modernization of the Nagornaya heat and power plant: the subsidiary company TER-NN terminated its contract with ASB Parsek LLC and signed an agreement with TGV-Proektirovanie LLC.[2] The second count concerns a contract for relaying heating networks with Stroitelnye Tekhnologii LLC: investigators consider it a violation that a sole supplier was chosen even though the company's director, Zoya Makarkina, had an unexpunged criminal record (a suspended sentence handed down in 2022), and that no penalty was collected for the delay in the work.[2] The third and fourth counts concern doubling the salary of TER-NN director Yakov Girkin. According to the investigation, the pay raise was made, among other reasons, so that Girkin could pay for a lawyer in his own criminal case for exceeding his authority.[1]

The position of the defense

Khalturin and his lawyers do not admit guilt. According to the motion, the delays by Stroitelnye Tekhnologii LLC in relaying the networks were due to the workload of the state expert review body, as well as to simultaneous work by gas and road services at the same sites.[2] Regarding the criminal record of the director, Zoya Makarkina, the former head of Teploenergo stated that he learned of it only in 2023 — when, because of sanctions, the company switched to sole-supplier contracts and Makarkina asked that payments be sent to the accounts of ST LLC, which was registered in the name of her minor son, citing problems with the tax authorities.

As for the contract with Stroitelnye Tekhnologii LLC, Khalturin clarified that the director's criminal record became known in 2024, after which no new contracts were concluded with the firm; tenders for the work were announced repeatedly, but no bids were received from other participants.[3][2] Khalturin explained Girkin's pay raise as a need to retain a manager who intended to leave because of the heavy workload — so as to avoid disrupting the reconstruction of the plant. In court, Khalturin described the raise in stages: first the salary was increased to 140,000 rubles, then to 290,000 rubles; according to the defendant, the decision did not contradict the company's charter or the Labor Code, and after his dismissal the new head of Teploenergo independently invited Girkin back and raised his salary again.[3][2]

Witness testimony

At a repeat examination in court, Yakov Girkin confirmed his complaints against Parsek: delays in preparing the project, entire sections of documentation missing, technical errors, and subsequently the contractor's cutting off contact.[2] The director of ASB Parsek, Alla Nemudrova, presented a different version: according to her, the delays were caused by deliveries of experimental boilers, changes to the project parameters by the client, and the filing of corrections as complaints; she also noted that Teploenergo had tried to complete the design and construction in two years instead of the standard three, and that the reconstruction of the Upper Town heating plant had been carried out without a construction permit.[2]

Shortly before the motion was filed, Yakov Girkin's criminal record was expunged in his own case of abuse of authority, for which he had earlier received a suspended sentence of 1.5 years. The prosecutor's office demanded a five-year prison term in a general-regime penal colony for Khalturin. In addition, the prosecutors requested a two-and-a-half-year ban on holding managerial positions in commercial organizations and compensation of 19.4 million rubles to the city budget.[3][4] During the court hearings, Khalturin stated that there had been no damage to the city treasury, and that after his detention in mid-2024, not a single agreement with the contractors had been terminated and no sanctions had been applied to them.

According to Khalturin, the Upper Town heating plant is the largest in Nizhny Novgorod, and the reconstruction was accepted in full.[3][4] The trial has lasted about a year; earlier in the hearings, Khalturin noted that he had worked in managerial positions for more than 14 years. In his closing statement, Khalturin rejected the investigation's version of his motive — a desire to keep his post for the sake of a salary — pointing out that receiving compensation for one's work cannot be considered an unlawful motive.[3][4][2]

Sources

  1. HyperNN — Defense asks for the criminal case against the former head of Nizhny Novgorod's "Teploenergo" to be dropped (archive)
  2. NIA "Nizhny Novgorod" — Defense of former "Teploenergo" head Khalturin asks to terminate the criminal case (archive)
  3. Open Nizhny — During closing arguments, the prosecutor's office requested a five-year sentence in a general-regime penal colony for Khalturin, along with a two-and-a-half-year ban on holding managerial pos
  4. Newsroom24 — Prosecutors demanded a five-year sentence in a general-regime penal colony for Khalturin.
  5. Newsroom24 — Defense of former "Teploenergo" head Khalturin asks the court to close the criminal case (archive)
  6. Open Nizhny — Defense of former "Teploenergo" head Khalturin asks to terminate the criminal case (archive)